Economy22 November 20263 min read
Small Hydro Power scheme targets 1,500 MW of new capacity
The Government of India approved the Small Hydro Power (SHP) Development Scheme for FY 2026–27 to FY 2030–31, with an outlay of ₹2,584.60 crore and a target of adding about 1,500 MW of capacity. It focuses on hilly, North-Eastern and border regions, where difficult terrain can constrain project development and electricity access.
About small hydropower
Small Hydro Power (SHP) covers projects with an installed capacity of up to 25 MW. These projects use the natural flow of rivers and canals to generate electricity. The Ministry of New and Renewable Energy is responsible for SHP projects, while projects above 25 MW fall under the Ministry of Power.
A run-of-the-river project generates electricity by diverting part of a river’s natural flow through channels and pipes to turbines, then returning the water to the stream. It does not require large dams.
Key features of the scheme
The scheme aims to address financing, project readiness and execution constraints, particularly in challenging geographies. Its main provisions include:
- An outlay of ₹2,584.60 crore for FY 2026–27 to FY 2030–31.
- A target of adding about 1,500 MW of SHP capacity.
- Financial assistance focused on hilly, North-Eastern and border regions.
- Support for project preparation and technical capacity building.
Regional distribution of small-hydro potential
India’s identified potential is 21,134 MW across 7,133 sites. As of 30 September 2026, 5,182 MW, or about 25%, had been harnessed, leaving 15,952 MW.
| Region | Potential (MW) | State-level potential (MW) |
|---|---|---|
| North | 8,030 | Himachal Pradesh 3,460; Uttarakhand 1,664; Jammu and Kashmir 1,312; Ladakh 396 |
| North-East | 2,995 | Arunachal Pradesh 2,065; Meghalaya 230; Assam 202; Nagaland 182; Mizoram 169; Manipur 100; Tripura 47 |
| South | 5,490 | Karnataka 3,726; Keralam 647; Tamil Nadu 604 |
| East | 1,707 | Bihar 527; West Bengal 392; Odisha 286; Sikkim 267; Jharkhand 228 |
| West | 2,912 | Chhattisgarh 1,098.20; Madhya Pradesh 820; Maharashtra 786 |
The North has the largest stated potential, though utilisation remains moderate. The South has relatively higher utilisation, supported by stronger infrastructure and grid connectivity. In the West, installed capacity stands at 730 MW. Maharashtra and Gujarat have relatively higher utilisation, while other areas retain scope for expansion.
Significance
SHP can provide reliable, round-the-clock electricity close to where it is consumed. In remote and hilly areas, decentralised generation can improve energy access and reduce dependence on long transmission networks. It can also contribute to grid resilience, local investment, employment, regional infrastructure and livelihoods.
Compared with large hydroelectric projects, SHP installations generally require less land and can involve relatively limited displacement. In rural and tribal areas, decentralised projects can support local energy access and economic activity.
Implementation challenges
Financing, project readiness and execution are constraints, particularly in difficult terrain. These can affect the development of a steady pipeline of viable projects. In the North, moderate utilisation indicates that identified potential has not fully translated into installed capacity.
The North-East’s remote and tribal areas present a distinct access challenge. Improved connectivity and decentralised solutions are important to expanding SHP there.
Way forward
Approaches identified for wider deployment include:
- Targeted financial support and incentives, along with simplified procedures.
- Project-preparation assistance and technical capacity building.
- Public-private collaboration and improved connectivity.
- Community-driven and off-grid models in the North-East.
- Optimisation of existing assets in the South.
- Canal-based and dam-toe projects in the West, using existing water infrastructure.